![none](https://costantini.eu/wp-content/uploads/2023/01/DJI_0375-scaled.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Costantini-Drone-1206.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Costantini-Drone-1211.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/DSC01239.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Niederkorn-1127.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Mathendahl-2843-scaled.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Mathendahl-2826-scaled.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Mathendahl-2817-scaled.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Niederkorn-1131.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Niederkorn-1145.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Niederkorn-1148.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Mathendahl-2847-scaled.jpg)
![none](https://costantini.eu/wp-content/uploads/2023/01/Mathendahl-2857-scaled.jpg)
RÉSIDENCE MATHENDAHL
Niederkorn
Travaux de gros-oeuvre et terrassement pour la réalisation d’un ensemble de 3 résidences comprenant logements et commerces sur sous-sol commun
Éléments clés
Blindage berlinoise
- SHOB GO : 10 800m²
- Volume terrassements : 12 000m³
- Béton : 5 200m³
- Acier : 750 to
Partager ce projet
- Domaine d'activités : Construction
- Agence : Costantini S.A.
- Début des travaux : Juillet 2021
- Fin des travaux : Avril 2022
- Maître d'ouvrage : Fonds du logement
- Maître d'oeuvre: JIM CLEMES ASSOCIATES